• About
  • Advertise
  • Privacy Policy
  • Contact
Monday, November 16, 2026
  • Login
The Vaultz News
  • Top Stories
  • News
    • General News
    • Education
    • Health
    • Opinions
  • Economics
    • Economy
    • Finance
      • Banking
      • Insurance
      • Pension
    • Securities/Markets
  • Business
    • Agribusiness
    • Vaultz Business
    • Extractives/Energy
    • Real Estate
  • World
    • Africa
    • America
    • Europe
    • UK
    • USA
    • Asia
    • Around the Globe
  • Innovation
    • Technology
    • Wheels
  • Entertainment
  • 20MOBPL2DNew
  • Jobs & Scholarships
    • Job Vacancies
    • Scholarships
No Result
View All Result
The Vaultz News
  • Top Stories
  • News
    • General News
    • Education
    • Health
    • Opinions
  • Economics
    • Economy
    • Finance
      • Banking
      • Insurance
      • Pension
    • Securities/Markets
  • Business
    • Agribusiness
    • Vaultz Business
    • Extractives/Energy
    • Real Estate
  • World
    • Africa
    • America
    • Europe
    • UK
    • USA
    • Asia
    • Around the Globe
  • Innovation
    • Technology
    • Wheels
  • Entertainment
  • 20MOBPL2DNew
  • Jobs & Scholarships
    • Job Vacancies
    • Scholarships
No Result
View All Result
The Vaultz News
No Result
View All Result
in General News

First Phase of U/E water supply project nears completion- Project Manager

Maynard Championby Maynard Champion
August 5, 2021
Reading Time: 4 mins read
Add as Preferred on Google
First Phase of U/E water supply project nears completion- Project Manager

Water supply pipelines

The Manager of the Upper East Regional Water Supply project, Annelies De Beule, has indicated that work on the first phase of the new water treatment plant at Tono in the Kassena-Nankana Municipality is 96 percent complete.

Speaking during the tour of the facility, she said the treatment plant which has a pumping station and raw water transmission pipeline, when completed, would have the capacity to produce 20.5cubic metres of water per day.

Annelies De Beule said this when she showed Mr. Amidu Chinnia Issahaku, the Deputy Minister of Water and Sanitation, and Mr. Stephen Yakubu, the Regional Minister round the facility and also disclosed that,; the handing over is scheduled for the end of October 2021.

The Deputy Minister was on a working visit to the Region to inspect ongoing works on water projects at Tono and Zuarungu in the Bolgatanga East District. He also, as part of his tour, visited the old water treatment plant at Vea in the Bongo District.

ADVERTISEMENT
WhatsApp Image 2021 08 05 at 2.57.46 AM
Manager of the Upper East Regional Water Supply project, Annelies De Beule
Second phase 69% complete

On the second phase of the project, Annelies De Beule said it was 69 per cent complete and would consist of a nine kilometre transmission line to Zuarungu, an upgrade of the connection to Bongo, 53 kilometres of distribution lines, one elevated reservoir at Zuarungu of 400 metre square, and the installation of 4800 house connections.

Touching on the other water treatment project, Annelies De Beule said the rehabilitation of the existing Vea water treatment plant would continue after the Tono treatment plant is fully operational.

She therefore noted that a total of 67 kilometres of the main transmission lines to Navrongo, Bolgatanga, Tindonmolgo, and Paga has been completed.

“18km of distribution lines have been installed under this phase, with one elevated reservoir at the Navrongo District Assembly (DA), with a capacity of 600 metre square.
A booster pumping station to Paga is also constructed at the DA. All existing reservoirs in the system have been rehabilitated.”

Annelies De Beule
bc5acd1a 2e41 4404 943f fa8f0d93a4d1
Mr. Amidu Chinnia Issahaku, the Deputy Minister of Water and Sanitation
Complete project within time frame

In an interaction with the media also, after the tour of the projects, the Deputy Minister for Water and Sanitation, Mr Amidu Chinnia Issahaku said work done on the project so far has massively progressed.

He however called on the contractors in charge of the project to ensure that the project is handed over within the time frame.

ADVERTISEMENT

Mr. Issahaku further indicated that the project upon completion would benefit a total of about 350,000 residents in the Region.

The Regional Minister, Mr. Stephen Yakubu adding his voice expressed satisfaction with the project and thanked the sector Ministry and Deputy Minister for his visit.

He then allayed fears of residents that there would be disruption in the water supply as work progressed.

ADVERTISEMENT

“As a Region, we are very happy that we have such a huge project that has come to us. The entire Region will have good drinking water and we are happy.”


Mr. Stephen Yakubu

The project, which started in 2018 and is expected to be operational in September 2021, is financed by the Ghana and Dutch governments.

It consists of two phases, the contract sum for the first phase is 33,250,000 EUR while the second phase which started on January 12, 2021, and expected to be completed in 12 months, also at a contract sum of 6,205,43121 EUR.

Read Also: There are Millions of Job Opportunities in the Maritime Industry – Transport Minister
ADVERTISEMENT

Sign Up to Our Newsletter

Fresh updates, Straight to your inbox

Tags: general newsGhana NewsMinistry of Sanitation and Water ResourcesUpper East RegionWater supplyWater Supply Improvement Project (WSIP)
Please login to join discussion
Previous Post

Rihanna officially declared a billionaire by Forbes

Next Post

Asante Gold to acquire Resolute’s Bibiani Gold Mine for US$90 million

Related Posts

Dr Theo Acheampong
General News

2027 Budget Signals Ghana’s Resolve To Preserve Economic Stability

November 16, 2026
Toyota Voxy
General News

Toyota Voxy Restrictions Await NRSA, Transport Ministry Deliberations

November 16, 2026
Principal Midwifery Officer at the Greater Accra Regional Hospital, Felicia Martey Dodoo
General News

Maternal Healthcare Requires Shared Responsibility Between Partners – Midwife

November 16, 2026
Director of Information Technology for the New Patriotic Party (NPP) and former Chief Executive Officer of the Ghana Integrated Aluminium Development Corporation (GIFFEC), Prince Ofosu-Sefah
General News

Ofosu-Sefah Questions New Economy’s Impact on Jobs, Growth

November 16, 2026
ADVERTISEMENT

Sign Up to Our Newsletter

Fresh updates, Straight to your inbox

ADVERTISEMENT

Recent News

Alhaji Aliko Dangote, Founder and President of Dangote Group

Dangote Explores Africa’s Investment Future

November 16, 2026
Dr Theo Acheampong

2027 Budget Signals Ghana’s Resolve To Preserve Economic Stability

November 16, 2026
Hon. Joseph Nelson, Western Regional Minister at Sankofa site

Our People Have Capacity to Manage Our Resources — Western Regional Minister

November 16, 2026
La Victoria

Popular Ghanaian Adaptation of ‘La Victoria’ Returns Free

November 16, 2026
image 137

Three Major Problems Cited For Manchester United’s Struggles

November 16, 2026
ADVERTISEMENT
Next Post
mining sector

Asante Gold to acquire Resolute’s Bibiani Gold Mine for US$90 million

The Vaultz News

Copyright © 2025 The Vaultz News. All rights reserved.

Navigate Site

  • About
  • Advertise
  • Privacy Policy
  • Contact

Follow Us

Ok

Retrieve your password

Please enter your username or email address to reset your password.

Log In
No Result
View All Result
  • Top Stories
  • News
    • General News
    • Education
    • Health
    • Opinions
  • Economics
    • Economy
    • Finance
      • Banking
      • Insurance
      • Pension
    • Securities/Markets
  • Business
    • Agribusiness
    • Vaultz Business
    • Extractives/Energy
    • Real Estate
  • World
    • Africa
    • America
    • Europe
    • UK
    • USA
    • Asia
    • Around the Globe
  • Innovation
    • Technology
    • Wheels
  • Entertainment
  • 20MOBPL2D
  • Jobs & Scholarships
    • Job Vacancies
    • Scholarships

Copyright © 2025 The Vaultz News. All rights reserved.

This website uses cookies. By continuing to use this website you are giving consent to cookies being used. Visit our Privacy and Cookie Policy.