The government has terminated the contract for the Nima-Paloma drainage upgrade under the Greater Accra Resilient and Integrated Development (GARID) Project after the contractor recorded less than 10 per cent progress on major construction components.
Minister for Works, Housing and Water Resources Kenneth Gilbert Adjei disclosed the development in Parliament while responding to questions on the project’s status and measures being taken to address flooding along the Nima-Paloma to Odaw Basin stretch.
The project, which involves constructing a 1.5-kilometre box culvert from Nima-Paloma to the Odaw River, commenced in July 2024 with an 18-month completion period. However, the minister explained that the contractor’s performance fell significantly below expectations, resulting in the termination of the agreement and plans to repackage the remaining works for a new procurement process.
Project Progress Remains Below 10%
Providing details on the state of completion, Mr Adjei outlined the limited progress achieved before the contract was terminated. Excavation works had reached 13 per cent, while demolition of the existing drain stood at 25 per cent.
Casting of concrete beds and walls recorded 9.7 per cent and 9.5 per cent progress respectively. The minister expressed concern that a project expected to be completed within 18 months had remained substantially unfinished after more than two years.

“A contract that was supposed to take one and a half years. We are in the third year and the progress of work is 9.7, 9.5, which I have enumerated. So, clearly, the non-performance.”
Minster of Works, Housing and Water Resources, Hon. Kenneth Gilbert Adjei.
The termination has left critical sections of the drainage infrastructure incomplete, raising concerns about the exposure of adjoining communities to flooding, particularly during heavy rainfall.
Repackaging Awaits Finance Ministry Authorisation
The Ministry is preparing to re-tender the project but requires commitment authorisation from the Ministry of Finance before proceeding with the procurement process. Mr Adjei explained that the request had been submitted within the past few months, although he could not immediately provide the exact date.
He attributed some of the challenges affecting public infrastructure contracts to contractors submitting exceptionally low bids to win tenders, only to discover that the agreed prices may not be commercially sustainable during execution.
According to him, some contractors have subsequently struggled to complete projects under such arrangements, prompting the government to terminate certain contracts. The minister maintained that the Nima-Paloma contract was terminated because of poor performance and not an underhand arrangement, adding that the project’s World Bank financing remained available.

He assured Parliament that the Ministry would work with the relevant stakeholders to secure the required authorisation and procure a new contractor to complete the outstanding works.
Emergency Measures Introduced to Reduce Flood Risk
While awaiting the procurement process, the Ministry has undertaken temporary interventions to improve water flow and reduce the immediate flood risk in affected communities. The minister disclosed that dredging and cleaning activities had been carried out along the drain to improve its capacity to convey runoff.
Additional local measures have also been introduced around upstream and downstream sections where previous construction activities had been initiated but left incomplete. These interventions are intended to limit the exposure of residents while the government works towards restarting the project under a new contract.
The Nima-Paloma drainage upgrade forms part of GARID, a World Bank-supported programme aimed at improving flood risk management, drainage infrastructure and urban resilience in Greater Accra.
GARID Flood Mitigation Works Continue Across Accra
Beyond the stalled Nima-Paloma project, the GARID programme includes several structural and non-structural interventions across the Odaw Basin. Ongoing and prioritised works include dredging the Odaw River and selected tributaries, improvements to the Odaw Channel at Abufu, the Kandeshi Drain and Channel Lot 2, and reconstruction of the Domi Road Bridge.

Other proposed interventions awaiting commitment authorisation include the Abusu-Ukai Bridge reconstruction, Atomic East and West detention ponds, Alajo Drain improvements and the Accra Flood Early Warning System Centre. The Ministry is also advancing a region-wide flood early warning system expected to provide improved forecasting and alerts to communities vulnerable to flooding.
The stalled Nima-Paloma project has renewed attention on contractor performance, procurement practices and the pace of flood mitigation infrastructure delivery. With the original contract terminated and a new procurement process yet to commence, residents along the drainage corridor are awaiting assurances that the remaining works will be completed before future rainy seasons intensify flood risks.